Question1: You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the two outputs of this process is change requests. Which one of the following is the other one?

Question2: Your program has just been chartered during the program initiation process. Your program also needs to create three program statements. Which program statement defines how your program will manage tradeoffs, competing objectives, and program and organization decisions?

Question3: Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?

Question4: You are the program manager for your organization. One of the projects within your program is to install
15,000 light fixtures throughout your organization's corporate campus. The new fixtures will save on electrical costs. Which one of the following choices is an ideal approach to quality assurance and the installation of the light fixtures for this project team?

Question5: Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Question6: A program with objectives that impact a large segment of the population receives negative commentary from organizations representing the public interest.
What action should the program manager take first?

Question7: A company hires a program manager to create a healthcare management system. After five months, the program manager identifies an opportunity to integrate an online medical solution, which could provide additional value to the stakeholders. The program sponsor approves the change in scope.
The program manager should ensure that the results obtained by this opportunity are working in tandem with which of the following?

Question8: Which of the following documents describes the details for each component in the WBS?

Question9: You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled.
Which one of the following is not something you'll have to monitor and control as a program manager?

Question10: You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

Question11: Over the life of your program you've received many change request forms. Some of the change requests have been approved and some have been declined. Where should you record all change requests and their status?

Question12: A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

Question13: Which of the following statements are true regarding program scope statement? (Choose three.)

Question14: Your program will create new software and install new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction. These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals?

Question15: A new program manager joins a multi-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization.
At the next stakeholder meeting, what should the program manager present to address their concerns?

Question16: You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?

Question17: A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST).
What should the program manager update?

Question18: You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?

Question19: Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance.
To resolve this situation, which of the following must go through critical review and change?

Question20: You are the program manager for your organization. You and your program team have been creating and transferring the program benefits to operations as feasible in your program execution. The process of delivering the program's benefits describes what process in program management?

Question21: You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?

Question22: At what point in the project is the risk of failing to achieve the project objectives the greatest?

Question23: Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

Question24: A program manager learns that their company's organizational strategy has changed. This change impacts one component project of a program, misaligning it with both the program objectives and the new organizational strategy. This component project, however, is already 90 percent complete.
What should the program manager do next?

Question25: You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

Question26: What quality control chart compares two or more variables over time to determine how closely the variables may be related to one another?

Question27: Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

Question28: Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete at this, but due to some vendor delays your program is running just a bit late. Management is concerned that your program will not be able to recoup the costs of the expenses.
They've asked you to determine the cost variance for the program. What is the cost variance based on this information?

Question29: A critical program for a company fails to delivers its intended benefits. The CEO and program sponsor are both held accountable and, ultimately, their employment is terminated by the board of directors.
What should the program manager do before formally closing the program?

Question30: You are the program manager for your program and are creating a communications management plan.
Management wants you to address the type of communications based on the number of communication channels you'll have within the program. Currently there are 345 stakeholders in your program but next week you'll have 387 stakeholders. How many more communication channels will you have next week in your program?

Question31: A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained.
What is the program manager's next step?

Question32: You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign?

Question33: A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts or left the company. Several new members have joined, but have a short association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.
How should the program manager handle this situation?

Question34: You are the program manager for your organization and you are preparing to launch several constituent projects within your program. You need to ensure that each project manager is authorized to utilize the appropriate project and program resources in order to complete the project requirements. What document do you need to create for each constituent project in your program to ensure that each project manager can use the appropriate resources?

Question35: An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.
What should the program manager do next?

Question36: A program manager initiates a new global program to create a higher level of protection for a company's intellectual property. The company exhibits a relaxed culture and environment, and is intolerant of processes to the point of being considered process-adverse. However, the company's culture is tolerant of long-term program activities, provided there is continuous progress on improving the protection of its intellectual property. Expectations for rapid progress are low.
What should the program manager do next?

Question37: You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?

Question38: You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

Question39: You are the program manager for your organization. Management would like to consider the present value for your program. If your program is predicted to be worth $450,000 in two years what is the present value of the program if the interest rate is six percent?

Question40: In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors.
There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

Question41: According to Standard for Program Management, Second Edition, how many knowledge areas are involved for program management?

Question42: You are the program manager for your organization and are working with your program team to create the program scope. Based on the program requirements you have identified the major deliverables of each phase in your program scope. Management has requested that you plan for cost estimating to happen at each phase of the program before continuing the work. Management may elect to cancel the program at the end of each phase based on past performance of the program. What are the reviews of management called at each phase?

Question43: You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?

Question44: Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?

Question45: Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their choices to either carpet or tile. The two acceptable choices of carpet or tile during scope definition is an example of what planning approach?

Question46: You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done. You want to ensure that mistakes do not enter into the project. What type of action have you provided in this scenario?

Question47: A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.
Which of the following deliverables captures these items?

Question48: You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program's life cycle except for which one?

Question49: During the selection of source process, you assign certain points towards various categories to judge the vendors. Which type of source selection process is it?

Question50: You are coaching Tammy, a project manager in your program, on the benefits of program management. She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

Question51: A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.
What should the program manager do NEXT?

Question52: An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately, what appeared to be a significant risk resulted in a negligible risk.
What should the program manager recommend to stakeholders for future, similar situations?

Question53: Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

Question54: You are the program manager for your organization. Your current program is to create a new recreational facility in your city. Franklin, the Chief Executive Officer, is concerned about meeting all of the financial and schedule requirements of the proposed program. Martina, the mayor of your town, wants to make certain the program meets all safety requirements and building codes. Your supervisor, Mary Ann, is the Program Director, and she is concerned about the start date of your program. Another stakeholder, Hal, is worried that your resources may be spread thin on the program as some of the resources are on multiple projects in your program.
To whom will you report to in this program?

Question55: Which of the following is used to build consensus through rounds of anonymous surveys?

Question56: A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.
How should the program manager demonstrate the program's progress?

Question57: Which of the following shows the ratio between a task's budgeted and actual costs?

Question58: You are the program manager for your organization. You have proposed a program that will cost $750,000 and will last for four years. Management is concerned with the cost of the program in relation to the return your program will bring. If the rate of return is six percent what is the minimum value your project should return in four years based on the investment of the program?

Question59: Which of the following documents sets the project objectives?

Question60: Program manager B leaves the program and program manager A takes over the program responsibilities.
Program manager A wants to ensure that all expected benefits of the program are realized.
What is used to assess the program cost/benefit justification?

Question61: An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However, the business team does not report to the IT program manager, and only two business team resources with the appropriate skills are available to complete the required program tasks.
To address this issue, what should the IT program manager do next?

Question62: The program manager defines the program objectives, requirements, and develops a high-level road map.
To ensure program alignment with the enterprise strategic plan, the program manager should work with which of the following?

Question63: You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

Question64: You are the program manager for your organization and your team has reported on a new issue among your program stakeholders. You want to address this issue as soon as possible, but it will need to be studied and reviewed. You recommend that Shirley, one of your program team members, study the issue and present a few solutions in a week's time. What else should you do with the issue?

Question65: You are the program manager for your company and evaluating the sellers to determine the seller to buy from.
In your analysis you've created a histogram to display the pros and cons for each seller. You've created five categories of interest and assigned values to each category for each vendor. Your five categories are:
* Cost
* Schedule
* Experience
* Certification
* Warranty
Each category has a different point value and the vendor that receives the maximum points in total will win the contract. What type of seller evaluation are you performing?

Question66: The new performance financial system is delivered to all business entities on time following a one-year implementation program. After six months of utilization the global finance department, one of the main beneficiaries of the program, determines that quality and level of granularity of the financial data is not sufficient for them to analyze the key performance indicators (KPIs) defined. Additionally, the global finance department is missing the analytical tools required to understand the causes of discrepancies.
To address these shortcomings, the global finance department submits a request for a follow-up initiative through the process defined by which of the following documents?

Question67: During a program's definition phase, it is determined that the best approach for delivering the program's intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers.
The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?

Question68: An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback. As this type of program had previously been conducted by the company, the program manager questions whether similar results were experienced during testing.
What should the program manager do next?

Question69: A newly appointed country manager suggests that the regional program manager use a social media platform to expedite communications and address questions. The new country manager used this social media platform at a previous job.
What should the regional program manager do to address the country manager's request?

Question70: There are five stages of team development. At which stage are there likely to be disagreements and struggle for roles in the program team?

Question71: A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?

Question72: Kelly's program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They've asked Kelly to use a schedule duration compression technique that will help the program finish on time. The technique that Kelly can use, however, should not add costs to the program. What duration compression technique should Kelly use in this instance?

Question73: A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder, but is unable to reach a compromise on the requirement.
What should the program manager do first?

Question74: Complete the following phrase about quality management: Quality isinto a program, notinto a program.

Question75: You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

Question76: Wanda is the program manager for her organization. Her program team consists of resources from across the organization - many of whom have not worked together before. Wanda thinks that she'll need to complete some team development but would like to focus the development on the materials and activities that the program team will need to complete in the program. What plan should Wanda reference and update to complete her team development process?

Question77: A component project of a program is completed, and will provide the intended incremental benefits.
How should the program manager proceed with the component transition?

Question78: If a risk has a probability of 60 percent and an impact of -$57,000 what will the expected monetary value of the risk event be?

Question79: The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?

Question80: Which one of the following is not an output of the direct and manage program execution process?

Question81: A component project of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations.
What should the program manager do next?

Question82: After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.
What should the program manager do next?

Question83: In a program's definition phase, a program manager in country A is assigned to expand a restaurant chain into country B.
The program manager creates the program team by identifying the required project management resources.
Which of the following represents an initial step needed to evaluate available resources that are aligned with the program's needs?

Question84: Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?

Question85: You are the program manager for the GHT Program for your company. This program has a budget at completion of $789,000 and is currently 40 percent complete, though it was scheduled to be 50 percent at this time. Your program has spent $325,000 of the budget to date. Based on this information, how many pennies is your program losing per dollar spent on the work?

Question86: Which of the following is not a template element that is designed to make the project more effective?

Question87: A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits.
What should the program manager do to address these key stakeholders' concerns?

Question88: Ben is the program manager for his organization. He's working with program team to determine what activities need to be completed in order to move the program into execution. He and the team are subdividing the program scope into smaller, manageable components to determine the activity list. What is Ben and his program team creating by subdividing the program scope in this scenario?

Question89: A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Tracking and reporting of actual benefits realized is one part of the review.
What is the other part of the review?

Question90: A program manager recognizes that a successful resource being used in project A could also be used in project B.
What should the program manager do first to leverage the utilization of this resource?

Question91: You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time. What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?

Question92: You are the program manager for your project. You are working with the project managers regarding the procurement processes for their projects. You have ruled out one particular contract type because it is considered too risky for the program. Which one of the following contract types is usually considered to be the most dangerous for the buyer?

Question93: A program is in its last year of execution. The program manager will receive a performance bonus if executive leadership and the program steering committee determine that the program is a success.
How can the program manager justify receiving a performance bonus upon program closure?

Question94: Which of the following can be used to help you or other project managers on future projects?

Question95: You are the program manager for your organization and are working on gathering the requirements for a new solution and mission statement. There are several instances in the stakeholder pool where the stakeholders and their manager are being queried on possible requirements. You worry that the subordinates may have requirements, ideas, and suggestions to offer but they may be not submitting their thoughts because they do not want to contradict their managers. You believe you need a method to gather all requirements without the stakeholders having any fear of retribution. Which one of the following allows you to anonymously gather iterations requirements and still allow all stakeholders to review what has been submitted in an attempt to find consensus?

Question96: Which one of the following is the best example of transference?

Question97: You are the program manager of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

Question98: Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program.
This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?

Question99: You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent
$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, how many pennies is the program losing per dollar invested in the program work?

Question100: Which of the following represents the duration of activities against a calendar?

Question101: A program receives initial approval from the selection committee to proceed with the program development.
What should the program manager do next?

Question102: A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision:

Which project should the program manager select to be cancelled?

Question103: Which of the following can be an effective tool during quality control to help determine the how the problem occurred?

Question104: You are the program manager for your organization. You're currently creating an accountability matrix starting with yourself, the program manager and the program sponsor. What program management process identifies the program sponsor?

Question105: Don is the project manager of the NQP Project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. What document should Don reference for information on the activities and the regulations?

Question106: A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.
Which of the following deliverables captures these items?

Question107: The number of emerging risks increases in a component project and the program manager falls behind in reviewing and approving the plans. This impacts the component project manager's ability to effectively address the risks.
In this situation, what should the program manager change about the risk management plan?

Question108: Your company and a competing company have created a teaming agreement for an opportunity. Through this team agreement you and your competitor can complete a major program for a client. This is, technically, a risk response for both organizations. What type of risk response are you dealing with in this instance?

Question109: Which of the following contract types is described in the statement below?
"The seller is reimbursed for all allowable costs for performing the contract work, and receives a fixed payment calculated as a percentage for the initial estimated project costs."

Question110: The program manager has a global program with five component projects. The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs The program sponsor is new and has imposed these new requirements six months into a three-year program.
What should the program manager do next?

Question111: A program manager initiates a developmental program. Significant resources and funding are required for early activities until the program cost and budget estimates are complete.
What should the program manager do to understand the financial environment?

Question112: A program will generate revenue for several years after it ends. The program manager and the operations manager, who are accountable for managing the benefits after program closure, are in disagreement. The operations manager is concerned that information necessary for managing the processes and benefits after program closure will be unavailable. The program manager expresses that managing the benefits after program closure is not within the scope and must be managed through the scope management plan.
What should the program sponsor do?

Question113: You are the program manager for your organization. Your current program, which has just been initiated, needs to launch several projects in order to create all of the benefits of the program. What document do you need to create in order to initiate the projects within your program?

Question114: Rick is a Program Manager for a large construction program. The program contains four projects. Stakeholders have requested for some changes that will change the scope of the program. Rick needs to monitor and control program scope. He is required to analyze the change request with detailed deliverables, acceptance criterion, and the work of the program. Which of the following documents will help him for this?

Question115: The program manager completed the program's benefits analysis and planning activities.
What will this ensure for the program?

Question116: You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?

Question117: You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent
$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?

Question118: Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?

Question119: Which project management meeting allows stakeholders to meet one another and to learn about the project?

Question120: Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

Question121: What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Question122: A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.
To ensure the realization of long-term benefits, what should the program manager use?

Question123: Identify the term described in the statement given below? "The use of it should be reviewed along with an assessment of their effectiveness. This will aid the program management in determining if risks to the program are being effectively managed. It also provides feedback to the program management on any projects that need to be recovered or terminated."

Question124: A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?

Question125: You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?

Question126: A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment.
Where should the program manager document this?

Question127: You are the program manager for a large program in your matrix organization. You need to define when the resources in your program will be brought into the program and then released from the program so that the project managers, operational managers, and your program team can plan accordingly. What program management plan defines when resources are needed, how the resources will be obtained, and how the resources may be released from the program?

Question128: In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS).
During the meeting, the master scheduler indicates that the master program schedule should include which of the following?

Question129: You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?

Question130: Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?

Question131: Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week.
What must the new program manager do before program closure?

Question132: A large international manufacturing company is centralizing its IT which is currently spread over 16 countries.
The transition means physically regrouping the infrastructure and aligning processes and organizations. The high-level scope of this transformation encompasses three main areas:
1.The technology area--assessing which technology/tooling should be retained for the target data center.
2.The policies and procedure area--aimed at establishing a common set of processes supporting the new way of delivering services.
3.The HR area--assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions.
You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase.
Which document should be present in your business case?

Question133: During program execution, how does a program manager ensure that benefits are being realized in accordance with program governance?

Question134: You are the project manager for the GGG Project and are about to close the project kick off meeting. All of the project team members and the key stakeholders are in attendance. What final item should you talk about before closing the meeting?

Question135: Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

Question136: You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?

Question137: Which of the following is described in the statement given below?
"It serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication."

Question138: A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be
55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?

Question139: Who makes Go/No-Go decisions during phase gate reviews?

Question140: You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any questions the vendors may have about the project. What is this meeting called?

Question141: A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

Question142: After a company's senior executive management meeting, the CEO issues a mandate to automate a new- client on-boarding process that would effectively eliminate the current, manual, paper-based process. The assigned program sponsor selects a program manager.
Both the program sponsor and the program manager must ensure that the program charter contains which of the following?

Question143: What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

Question144: In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?

Question145: Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of the following is the best chart for Gina in this situation?

Question146: An experienced program manager is leading a development program in a new company. While reviewing company procedures for formulating a program, they discover there is no company practice for managing key suppliers.
What should the program manager do first to obtain program approval?

Question147: You are the program manager for the SRQ Program. You have rejected several change requests for the program scope. What must you do with the rejected change requests?

Question148: You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

Question149: Wan is the program manager for his organization. He has been hearing reports that some project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties.
You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

Question150: During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.
What should the program manager do?

Question151: Which of the following tools and techniques are parts of the Administer Program Procurements process? Each correct answer represents a complete solution. Choose all that apply.

Question152: In which of the following processes is the program charter created?

Question153: Which one of the following is not considered one of the three components of the Iron Triangle?

Question154: To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized.
What should the program manager do?

Question155: A program manager joins a team to fix a troubled enterprise-wide customer relationship management (CRM) system. Analysis indicates that duplicate customer information data is resulting in redundant client information. The program manager accesses the knowledge repository for similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity.
What should the program manager do with the knowledge gained from this activity?

Question156: Thequality assurance technique ensures continuous improvement of all processes.

Question157: All of the following are benefits of a program except for which one?

Question158: You are the program manager of the MQQ Program. Your program will use equipment and materials that are new to your industry. You have some concerns that there will be delays and waste by your program team because they've not worked with these materials or tools before. You elect to send the resources that will work the most with these tools through training. The cost of the training in this instance is known as which one of the following?

Question159: A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program's benefits sustainment and transition plan. What should the program manager do to create this plan?